- StudyBlue
- Texas
- Texas A&M University
- Construction Science
- Construction Science 253
- Segner
- QuizB(flashcard)
QuizB(flashcard)
Construction Science 253 with Segner at Texas A&M University
About this deck
By: JT Webb
Created: 2011-06-11
Size: 90 flashcards
Views: 11
Created: 2011-06-11
Size: 90 flashcards
Views: 11
About StudyBlue
STUDYBLUE makes things that make you better at school.
Things like online flashcards with photos and audio.
Things like personalized quizzes and friendly reminders about when (and what) to study next.
Think of it as a digital backpack™: access to all of your study materials online and on your phone.
STUDYBLUE exists to make studying efficient and effective for every student, for free. Join us.
“I have been getting MUCH better grades on all my tests for school. Flash cards, notes, and quizzes are great on here. Thanks!”
Kathy
Kathy
Sign up (free) to study this.
Handle/ Transport of Concrete
to avoid separation of course aggregate from mortar and of water from other ingredients. Segregation at point of discharge, avoided by down pipe at end of chute. Concrete should drop vertically into the center of receiving bucket, hopper, form
Ways Concrete is handle and Transported
- Chutes
- Push buggies
- Buckets handled by cranes
- Pneumatically forcing through a hose (shotcrete)(Gunnite)
Preparation
surfaces should be properly prepared, forms should be erected, reinforcement should be installed
Requirements Common to All Concrete-1
- Not be placed frozen subgrade(snow, ice, debris must be removed from forms, excavations and from slab beds
- When placed on rock, loose material removed, cut face vertical and horizontal rather than sloping
Requirements Common to All Concrete-2
-Chlorides not be used in concrete which dissimlar metals are embedded, reinforcing steel and heating ducts
-reinforcing steel should be clean and free of loose rust and mill scale at time concrete is placed
-Hardened mortar should be removed from steel
Slabs on Grade-1
- Subgrade should be trimmed to spec elevation, uniformly compacted
- except when vapor retarder, waterproof membrane, or separator has been installed below slab, subgrade should be moistened to prevent too rapid extraction of water from concrete
Slab on grade-2
- At time of placing concrete no mud, soft spots, or free water standing where concrete is to be placed
- PCA recommends vapor retarder on grade where impervious floor finish will be installed, where passage of water vapor is undesirable
Slab on Grade-3
- Though Vapor retarder placed in contact with concrete, causes excess moisture in the concrete to bleed to surface rather than downward, increasing capillaries in the concrete, weakening the surface, more cracking, higher permeability of the slab
Slab on Grade-4
PCA recommends vapor retarder not be placed directly beneath slab, instead covered by 3in thick layer of granular, self draining(sand)
-when not vapor retarder used, building paper can be used, installed between base course or fill and the slab, not in contact with slab
Curling
warping of the slab
Formed Concrete
- tight, adequately braced, constructed of material that impart the desired texture to the concrete
- remove dirt, nails, sawdust, wood chips
- treated with releasing agent (oil or lacquer)
- architecual concrete- agent non-staining lacquer, emulsified stearate
- wood forms moistened before concrete placed or they will absorb water from concrete and swell
Placing
- placed to point where concrete will stay as close as possible
- not in large quantities and allowed to run or worked over large distance
- mortar flows ahead of coarser material results sloping surface
- placed horizontal layers uniform thickness, each layer compacted before the next is placed
- layer must be placed before other layer hardens
Placing Systems
- Dumping from truck
- Buggy
- Dumping from truck to bucket, which crane lifts
- Dump from truck through hose
- Drop no more than 4 ft to prevent segregation
- Not strike against forms, drop chute should be used to prevent spattering of mortar
Order of Placing
- on walls, start at ends, work toward center
- slabs, start around perimeter
- Flat surface, start at far end so that each batch will be dumped against previously placed concrete, not away from it, should not be poured into piles and worked together
Order of Placing
- if stone pockets occur, remove larger particles and distributed to areas where more mortar present to surround them
- Walls, first batch placed at either end, then progress towards center
Placing on Hardened Concrete-1
- should be level, rough, clean, moist, some aggregate particles should be exposed
- Laitance (soft layer of mortar) removed from top surface
- appreciable thickness of laitance indicates that segregation and bleeding occurred or too much water was used
Prevention of Laitance
using stiffer mix or finer material , particularly in the upper part of the lift
Placing of Hardened Concrete-3
When new placed on old concrete, old must be roughened and cleaned thoroughly, sometimes whole top surface can be removed.
Placing of Hardened Concrete-4
placed on hardened concrete or brick, layer of mortar should be placed down to provide a cushion against new concrete to be placed. prevents stone pockets, endures tight joint. made of same concrete to be placed and slump of 6in. thickness of 1/2 to 1in. In two-course floor construction, coat of portland cement and water paste with consistency of thick paint should be brushed onto hard surface
Shotcrete
- pneumatically placed, primarily for swimming pools and in/above ground free-form structures and repair.
- not require form work
- through hose onto earth, rock, existing concrete, another layer of shotcrete
- Reinforced with bars, mesh, steel fiber
Shotcrete Finish
- Natural finish left by placement gun
- screeded finish by sharp-edge cutting screed
- flash coat by spraying on a final coat of shotcretejmade with fine aggergate
- float and trowel finsh, though not on thin slabs
Consolidating
Concrete should be compacted for
- eliminate stone pockets, large air bubbles
- consolidate each layer with one placed earlier
- completely embed reinforcing and fixtures
- bring just enough fine material to the faces and top surfaces to produce desired finish
Spading and Puddling
Medium to High Slump Concrete(3 to 8in) should be compacted and worked into place by spading or puddling.
Spades ans Sticks used that are long /thin enough to pass through steel and forms, should be used
Vibrating-1
Low to Medium (1 to 6in) mechanical vibrators within concrete (internal vibrator) top of concrete or on the forms(external vibrator). Thin slabs not heavily reinforced may be visbrated by beam or truss screeds. Thick slabs structural reinforcement and thicker concrete members, such footings, walls, columns beams, girders vibrated with internal vibrators
Vibrating-2
- friction between CA is temporarily eliminated, concrete behaves as liquid
- concrete settles in the forms under action of gravity
- trapped air bubbles rise more easily
- once vibration is stopped friction is reestablished
Vibrating-3
- less water per unit volume of portland cement, concrete will be of better quality
- less portland cement unit volume used, concrete will be more more economical
- vibrators should not be used to move concrete or push it
- Sufficient vibration is seen by mortar line along forms and coarse aggregate sinking below top surface
Finishing
Finished in severalways, depending on its location, concrete material used, esthetic effect desired
Finishing Standard weight Concrete slabs
Steps: screeding, leveling, edging, jointing, floating, troweling, broom finishing or surface texturing
Bleeding
- dry materials heavier than water so they settle to bottom, causing water to move towards surface= bleeding
- happens more often in non-air entrained
- scaling, dusting, crazing if worked on while bleeding is present
- most basic rule
- Placing, screeding, leveling must be done before it has the chance of happening
- Should not be placed faster than it can be spread, struck off, leveled
Screeding
screeding is where surface of newly placed concrete is struck off by moving straight edge back and forth like a saw motion. If mechanical vibrating equipment is used in screeding, leveling may not be needed
Small amount of concrete kept in front of straightedge to fill low spots
Greatest affect on surface tolerance
screeding the surface to a predetermined grade
Leveling-1
- bringing of a concrete surface to true grade with enough mortar to produce the desired finish
- after a slab has been screeded, use of Darby to level raised spots and fill depressions left after screeding
Bull Float
Long handled, either wood or metal, used sometimes instead of Darbies to smooth and level. Though hard to smooth edges so Darbies are needed then
Darbying or Bull Floating
Leveling is sometimes called Darbying or Bull Floating but if used both must be used or Architect must dictate which one is to be used and which one is inappropriate. PCA uses broader term "leveling"
Leveling-2
- purpose to eliminate the ridges and voids left by screeding.
- slightly embed the coarse aggregate, preparing the surface for subsequent finishing operations of edging, jointing, floating, troweling
- no operation can be preformed until concrete will sustain foot pressure with only about 1/4in indentation
Edging
- bleed water and water seen have left surface and concrete starts stiffen
- it rounds off the formed edge of a slab to prevent chipping or damage
- edger ran back and forth
- coarse aggregate covered
- not to deep of impression
Edging 2
- interior slab on grade doesn't need most of time
- most often preformed on sidewalks, driveways, and steps
- not used is slab is to be finished with resilient flooring requiring a smooth level subfloor
- edge on construction joints ground lightly with silicon carbide stone
Jointing
Except when joints will be later sawed, immediately following or during edging, premolded inserts are placed in concrete slabs to control cracking as results of shrinkage
Floating
- after edging and hand jointing, slab should be floated
- many variables affect process, concrete temperature, air temperature, relative humidity, wind
- Knowledge comes with experience, general though floating may be done when water sheen gone, concrete will hold weight finishing
Floating-2
purpose
- embed large aggregate just beneath surface
- Remove slight imperfections, humps, voids, produce a level or plane surface
- Consolidate mortar at surface in prep for other finishing ops
- Open surface to permit excess moisture to escape
Floating-3
- marks left by edgers and jointers removed by float
- floats made of aluminum or magnesium, especially on air-entrained concrete
- This type of float greatly reduces amount of work to be done, because slides easier over concrete, good floating action
Troweling
- done on slabs left to exposer, or receive thin finish( resilient flooring, carpet, title or paint
- when required, surface should be troweled immediately after floating
- customary for a cement mason using hand tools to float and then steel trowel before moving to knee boards
Troweling-2
If necessary, tooled joints and edges should be rerun before and after troweling to maintain true lines, proper depths and uniformity and remove kinks
Troweling-3
- purpose to produce smooth hard surface
- first troweling by power or hand, trowel must be kept flat, if not and tilted it may cause washboard or chatter
- First troweling, a new trowel not recommended
- Time lapse of time between troweling let concrete hardened
Troweling-4
- as surface stiffens, troweling should be made by smaller trowel tipped at progressively higher angle so that sufficient pressure can be applied
- seconde troweling recommend because it gives closer surface tolerances and better surface to receive flooring.
Broom Finishing
- slightly roughened to produce a non-slip surface by brushing or brooming them.
- brushed surface made by drawing a broom over surface after steel troweling
- work who can draw broom right over edge joint but joint not being marred, indicates proper steel trowel
Finishing Air-Entrained concrete slabs
- microscopic air bubbles hold the ingredients, including water in suspension
- requires less mixing water, still has good workability with same slump, little or no bleeding occures
- no need to wait for evaperation of free water, floating and troweling can be started soon as it can hold weight of person
Finishing Lightweight Structural Concrete
- tendency for the coarse aggregate to raise to the surface instead of falling, while the mortar raise
- to prevent 1. mix properly proportioned, not over/under sanded to meet weight stand. 2. finishing not started early, not overworked/ overvibrated
Finishing Lightweight Structural Concrete-2
well proportioned mix can be placed, struck off, leveled, floated with less effort than normal weight concrete
Excessive leveling, floating are principal causes of finishing problems because heavier mortar is driven down to the bottom, and CA to the top
Special Slab Finishes
suface may be scored or tooled with jointer in decorative and geometric patterns
Exposed Aggregate
- chosen for an area where special textural effect is desired
- selection of aggregate is so important that test panels should be made before job started
- should have colorful gravel, uniform in gradation, sizes ranging from 1/2 to 3/4 in
Exposed Aggregate-2
- Flat, sliver-shaped particles or aggregate less than 1/2 should be avoided
- 5 and one-half to six-sack concrete with max 3in slump should be used
- after slab is screed and leveled, aggregate spread by hand
- initial embeding done with darby or 2x4 by patting
Exposed Aggregate-3
- surface hand floated with float or darby, make sure all aggregate in fully covered, no holes, or openings in surface
- shortly after reliable retarder may be sprayed or brushed
- exposing time of aggregate very importpant, soon as grout covering aggregate can be remove by brush or hosing
Exposed Aggregate-4
- interior areas where smooth surface is desired, exposing aggregate is done by grinding, may be followed by polishing, which produce a similar product of terrazo
- Decortive or control joints, cut 4 to 12 hours after slab is placed, also 1/5 depth of slab
Exposed Aggregate-5
- small radius edger should be used before and after embedding
- another method installing redwood before placing concrete
- another method spreading a 1in thick top coarse
Dry Shake Colored Surface
- used for interior areas, terraces, decorative walks, driveways
- ingredients mineral oxide pigment, white portland cement, specially graded silica sand or fine aggergate
- select, proportioning, mixing at site not recommended
Dry Shake Colored Surface-2
- floated by hand or power
- if by hand, use magnesium or aluminum float, to bring up moisture for combining with dry shake, also removes ridges, dpression, dry shake by hand
- if wrong amount applied, peeling may occure
Dry Shake Colored Surface-3
- first application about two-thrids total needed, which is usually specified in pounds per square foot of surface
- after float and then trowel, there should be a lapse of time which depend on temp and humidity
Dry Shake Colored Surface-4
- Exterior surface two trowelings are enough,
- Interior should get a third, should be done by hand to produce hard, dense, wearing surface
- must be cured
- interior may be coated twice with concrete floor wax( same mineral oxide pigment)
Swirl Design
- nonskid surface texture produced on a slab using magnesium or aluminum float or steel finishing trowel
- called swirl float finish when float is used
- called swirl trowel finish when trowel is used
- work semicircular or fan like motion by cement mason
- moist curing finial operation
Keystone Finish
- produces a travertine like texture
- used terrace, garden walk, driveway, deck around swimming pool
- Not used where it is exposed to freeze/thaw
- after screeded, leveled, edged, then broomed with stiff broom to ensure that finish(mortar) bonds
Keystone Finish-2
- mortar coat made by mixing one sack white portland cement, 2 cu ft of sand, 1/2 lb of color pigment,
- Yellow is usually used
- Enough water added to make soupy mix like thick paint
Keystone Finish-3
- mortar placed in pails and thrown vigorously on slab with stiff brush called dash brush
- this produces uneven surface with ridges and depressions
- Ridges should be 1/4 to 1/2 high
Finishing Formed Surfaces
- depends on exposure and esthetic effect designer is trying to achieve
Rough Form Finish
- rough form finish left where formwork locations will not be seen in the building
- improve only by filling tie holes and defective areas, chipping off projections larger than 1/4 in
Smooth Form Finish
used two times
- when form liners are used to impart a pattern or texture
- when concrete will receive paint, waterproofing, dampproofing, veneer plaster, another thin coating or covering material
- tie holes patch or left alone, screw ties with cones used when ties not to be filled
Smooth-Rubbed Finish
- applied when smooth form or form liner used
- applied to moistened concrete within 1 day after forms removed and rubbing it with abrasive such as Carorundum brick
- Cement grout not used
Grout-Cleaned Finish
- used on concrete that has been placed against a smooth form or form liner
- apply thick-paint like grout of 1 part portland cement and 1 1/2 fine sand, mixed with equal part acrylic or styrene butadiene bonding material and water
- stand (gray) and white portland cement used to achive color
- completed by rubbing with burlap
Scaling
- breaking away of the hardened concrete surface of slab to depth 1/6 to 3/16
- occurs at early age of slab
- cycles of freezing/thawing, salts on non-entrained air concrete it happens
- preforming finsih operation while bleed or water on surface
Scaling-2
- not allowing bleeding or excess water to evaporate, cause segregation of surface, brings thin layer of neat portland cement
- water should be allowed to evaperate from surface or drag water hose across the top before finsihing
Crazing
- numerous fine hair cracks in the surface of newly hardened slab due to shrinkage
- looks like crushed egg shell
- result of rapid surface drying, caused by high temp, hot sun, drying winds
- lessened by curing with water
- over vibrating screed, darby, bull float by working excess mortar to top
Dusting
- powdery material on surface
- excess of harmful fines(clay or silt) in concrete mix with sand and cement at surface
- this problem emphasizes the use of clean, well-graded coarse and fine aggregate
Dusting-2
- carbon dioxide comes in contact with surface of plastic concrete, it impairs hydration
- Condensation usually occurs on surface during spring and fall
- concrete should be heated if this anticipated by hot water, or blower type heaters
- neat portland cement/mixtures/ fine sand never used as dry shake
Dusting-3
- well mixed dry mixture= 1 part portland cement and 1 part well-graded concrete sand
- winter heaters may lower relative humidity around concrete such as inhibiting hydration
Curing
- fresh concrete has more than enough water for hydration, but at job sites this is often lost by evaporation
- Hydration preceeds at much slower rate as temp drops until it reaches 14 degree which it stops all together. at 40degrees it is to slow to proceed
Curing Methods
- leaving forms in place
- sprinkling, ponding,
- use moisture-retention covers or a seal that goes on as liquid then makes hard thin layer
Leaving Forms in place
great way of keepinig water in, in hot dry weather, wood forms dry out and take water in from mixture. These should be kept moist by sprinkling
Sprinkling
- must be continuos, not allowing dry to happen between applications
Ponding
- used on flat-surfaces
- small dam of earth or other water-retaining material placed around perimeter of a surface and enclosed area is flooded
Curing Covers
- moisture-retaining covers such as wet sand, burlap, polyetgylene film
- kept constantly moist enough to provide flim
Watertight Covers
- used on floors and other horizontal areas, non-staining, strong enough to with stand wind and other factors. Seams should be overlapped several inches.
Sealing Compound
- sealing colors in red, colorless, white pigmented coatings
- some can be applied in one coat but two will give better results
- made immediately after concrete in finished, concrete kept moistened
- in hot weather, wet concrete for 12hrs before application
- covered by 1in of sand or earth or other means, though not sooner than 24hrs after sealing
Curing Temp
Refer to American Concrete Institute (ACI) ACI 305R and ACI 306
Cold Weather Construction
- often need to heat concrete ingredients
- in Cold weather concrete should have temp of between 50 to 70 f
- no cases should it be heated to above 70degrees, if so built in thermal stress will occur
- Should be kept between 50 to 70
Cold Weather Construction
- 70 degrees 3 days, 50 degrees for 5 days when type 1 is used
- 70 degrees 2 days, 50 degrees 3days when type III is used
- no dependence on salt or other chemicals
Mild Weather Construction
- weather is betw
Hot Weather Construction
- Definition
Length of Curing
- should last atleast 7 days no matter what kind of concrete
- in mild weather it can be reduced 2 days when type III
- temp not to draw below 50 degree
- rapid cooling may induce thermal cracking, especially during first 12 to 24hrs
Length of Curing -2
Type I- 5days 70 degrees
7days 50-70degrees
Type II-3 days 50 degrees
All other Types- 7days 70 degrees
14days 50-70 degrees
About this deck
By: JT Webb
Created: 2011-06-11
Size: 90 flashcards
Views: 11
Created: 2011-06-11
Size: 90 flashcards
Views: 11
About StudyBlue
STUDYBLUE makes things that make you better at school.
Things like online flashcards with photos and audio.
Things like personalized quizzes and friendly reminders about when (and what) to study next.
Think of it as a digital backpack™: access to all of your study materials online and on your phone.
STUDYBLUE exists to make studying efficient and effective for every student, for free. Join us.
“I have been getting MUCH better grades on all my tests for school. Flash cards, notes, and quizzes are great on here. Thanks!”
Kathy
Kathy